Phase 2 of the English translation: Word documents (filled, EPB-specific): - 8 plans (PID, PM, QA, SWE, Test, Project Manual, CM, RM) - 6 safety docs (HARA, Safety Case, FMEDA, MISRA Compliance, Verification Report, Tool Qualification Cppcheck) - 2 manuals (User, Service) - 3 audit artefacts (Review minutes, NC-001, MISRA-REC-001) - All regenerated via pandoc from English markdown sources Code, tests, headers: - All file headers, struct comments, function docstrings in English - All test names (TEST_BEGIN strings) translated - Inline comments translated - 46 tests still green after translation CI workflows: - All step names in English - Step descriptions, comments, release notes template in English README.md fully rewritten in English with proper guided tour. Phase 3 (still pending): dev-process repo templates + toolstack/setup docs.
5.0 KiB
5.0 KiB
doc-id, version, status, date
| doc-id | version | status | date |
|---|---|---|---|
| SLM-EPB-RM-001 | 1.0 | Released | 2026-05-12 |
Risk Management Plan (RM Plan)
| Field | Value |
|---|---|
| Project | demo-epb |
| Document ID | SLM-EPB-RM-001 |
| Version | 1.0 |
| Status | Released |
| Date | 2026-05-12 |
| Standard | ASPICE MAN.5 |
1. Purpose
Identifies, assesses, and treats project risks (organisational, technical, schedule, resource). Distinct from functional safety risks (hazards), which live in the HARA.
2. Methodology
| Step | Activity |
|---|---|
| 1. Identification | Workshops, lessons learned, stakeholder input |
| 2. Classification | Probability (P) × Impact (I) |
| 3. Assessment | Risk score = P × I (1-25) |
| 4. Treatment | Avoid / Mitigate / Accept / Transfer |
| 5. Monitoring | Quarterly review, status updates |
2.1 Classification scale
| Probability | Meaning |
|---|---|
| 1 | Very unlikely |
| 2 | Unlikely |
| 3 | Possible |
| 4 | Likely |
| 5 | Very likely |
| Impact | Meaning |
|---|---|
| 1 | Negligible |
| 2 | Minor delay / additional effort |
| 3 | Noticeable impact on schedule/budget |
| 4 | Significant impact, project at risk |
| 5 | Project stop |
| Score range | Action |
|---|---|
| 1-4 | Accept, monitor |
| 5-9 | Mitigate (plan) |
| 10-15 | Mitigate (immediate, with escalation) |
| 16-25 | Escalate to Project Owner |
3. Risk register
| ID | Description | P | I | Score | Treatment | Status |
|---|---|---|---|---|---|---|
| R-01 | Demo is mistaken for production-ready code | 3 | 3 | 9 | Disclaimer in README + Project Manual | Mitigated |
| R-02 | MISRA tooling update breaks CI (false positives) | 2 | 3 | 6 | Pin tool versions, regression suite | Mitigated |
| R-03 | Reviewer availability for ASIL-D | 3 | 4 | 12 | Self-review documented (demo only) | Accepted (demo) |
| R-04 | Gitea server outage | 2 | 4 | 8 | Local clones, regular backups | Mitigated |
| R-05 | Apple certificate expiry without warning | 3 | 3 | 9 | Renewal reminder + 30-day notice | Mitigated |
| R-06 | Windows build VM unreliable (busybox-PATH conflicts) | 4 | 2 | 8 | MSYS2 documented, alt PATH ordering | Open |
| R-07 | macOS act_runner host-mode cache bug | 3 | 2 | 6 | continue-on-error, documented | Open |
| R-08 | Doorstop tool compatibility on upgrade | 2 | 3 | 6 | Own traceability.py, no doorstop dep | Mitigated |
| R-09 | Knowledge loss with single-person setup | 4 | 4 | 16 | Maintain Project Manual + documentation | Open |
4. Risk reviews
| Frequency | Participants | Outputs |
|---|---|---|
| Quarterly | Project Owner + TL | Updated register, action items |
| On change | Affected roles | Risk score update |
| At release | Project Owner + QA | Residual-risk assessment |
5. Escalation path
Risk owner (daily)
│ Score > 9
▼
Project Owner (weekly)
│ Score > 15
▼
Stakeholder / Client (immediately)
6. Lessons learned
Closed risks are summarised at project closure under docs/lessons-learned/, to better assess follow-up projects.
7. Related documents
PM-Plan.docx— Top-level risks (summary)HARA.docx— Functional safety risks (hazards, separate from project risks)QA-Plan.docx— Non-conformity management
8. Revision history
| Version | Date | Change | Author |
|---|---|---|---|
| 1.0 | 2026-05-12 | First release | S. Lohmaier |