feat: Project Manual + CM-/RM-Plan + Landing-Page
Validate / build-test (macos-latest) (push) Failing after 2s
Validate / build-test (windows-latest) (push) Failing after 15s
Validate / build-test (ubuntu-latest) (push) Failing after 15s
Validate / reports (push) Has been skipped
Release / release (push) Successful in 57s
Validate / build-test (macos-latest) (push) Failing after 2s
Validate / build-test (windows-latest) (push) Failing after 15s
Validate / build-test (ubuntu-latest) (push) Failing after 15s
Validate / reports (push) Has been skipped
Release / release (push) Successful in 57s
3 neue Plaene: - Project Manual: Master-Wegweiser fuer neue Projektmitglieder, Lese-Reihenfolge, Rollen, Lebenszyklus, Dokumenten-Landschaft - Configuration Management Plan: CIs, Baselines, Change Control, Release-Prozess, Aufbewahrungsfristen (ASPICE SUP.8) - Risk Management Plan: Projekt-Risiken (abgegrenzt von HARA), Klassifikations-Skala, Risiko-Register, Eskalations-Pfad Landing-Page (Startseite): - tools/generate_landing_page.py erzeugt build/index.html - Standalone-HTML, oeffnet im Browser ohne Server - KPI-Cards: SG/SYS/SWE/Arch/Komponenten/Tests-Counts - Sektionen mit Links: Plaene, Safety, Manuals, Audit, Reports, Diagramme, Source-Code, externe Links - Existenz-Check: nicht-generierte Reports werden grau markiert - Im Release-Bundle als index.html ganz oben CI-Integration: - validate.yml: neuer Step "Landing-Page" + Upload als Artefakt - release.yml: Landing-Page generieren + ins Bundle einbauen, zusaetzlich Source-Code im Bundle (war vorher nur als tar.gz) Makefile: neues Target `make landing-page`
This commit is contained in:
@@ -0,0 +1,111 @@
|
||||
---
|
||||
doc-id: SLM-EPB-RM-001
|
||||
version: 1.0
|
||||
status: Freigegeben
|
||||
datum: 2026-05-12
|
||||
---
|
||||
|
||||
# Risk Management Plan (RM-Plan)
|
||||
|
||||
| Feld | Wert |
|
||||
|--------------|----------------------------------------|
|
||||
| Projekt | demo-epb |
|
||||
| Dokument-ID | SLM-EPB-RM-001 |
|
||||
| Version | 1.0 |
|
||||
| Status | Freigegeben |
|
||||
| Datum | 2026-05-12 |
|
||||
| Norm | ASPICE MAN.5 |
|
||||
|
||||
---
|
||||
|
||||
## 1. Zweck
|
||||
|
||||
Identifiziert, bewertet und behandelt **Projekt-Risiken** (organisatorisch,
|
||||
technisch, Zeitplan, Resource). Abgegrenzt von **funktionalen Sicherheits-
|
||||
Risiken** (Hazards), die im HARA behandelt werden.
|
||||
|
||||
## 2. Methodik
|
||||
|
||||
| Schritt | Aktion |
|
||||
|--------------------|-------------------------------------------------|
|
||||
| 1. Identifikation | Workshops, Lessons-Learned, Stakeholder-Input |
|
||||
| 2. Klassifikation | Wahrscheinlichkeit (W) x Auswirkung (A) |
|
||||
| 3. Bewertung | Risk Score = W * A (1-25) |
|
||||
| 4. Behandlung | Vermeiden / Mindern / Akzeptieren / Transferieren |
|
||||
| 5. Monitoring | Quartalsweise Review, Statusupdate |
|
||||
|
||||
### 2.1 Klassifikations-Skala
|
||||
|
||||
| Wahrscheinlichkeit | Bedeutung |
|
||||
|--------------------|----------------------------|
|
||||
| 1 | Sehr unwahrscheinlich |
|
||||
| 2 | Unwahrscheinlich |
|
||||
| 3 | Moeglich |
|
||||
| 4 | Wahrscheinlich |
|
||||
| 5 | Sehr wahrscheinlich |
|
||||
|
||||
| Auswirkung | Bedeutung |
|
||||
|------------|--------------------------------------------|
|
||||
| 1 | Vernachlaessigbar |
|
||||
| 2 | Geringe Verzoegerung / Mehraufwand |
|
||||
| 3 | Spuerbare Auswirkung auf Termin/Budget |
|
||||
| 4 | Erhebliche Auswirkung, Projekt gefaehrdet |
|
||||
| 5 | Projekt-Stop |
|
||||
|
||||
| Score-Bereich | Aktion |
|
||||
|---------------|------------------------------------------|
|
||||
| 1-4 | Akzeptieren, monitoren |
|
||||
| 5-9 | Mindern (Plan) |
|
||||
| 10-15 | Mindern (sofort, mit Eskalation) |
|
||||
| 16-25 | Eskalation an Project Owner |
|
||||
|
||||
## 3. Risiko-Register
|
||||
|
||||
| ID | Beschreibung | W | A | Score | Behandlung | Status |
|
||||
|-------|---------------------------------------------------------|---|---|-------|------------------------------------------|----------|
|
||||
| R-01 | Demo wird als produktreifer Code missverstanden | 3 | 3 | 9 | Disclaimer im README + Project Manual | Mitigated |
|
||||
| R-02 | MISRA-Tooling-Update bricht CI (false positives) | 2 | 3 | 6 | Tool-Versionen pinnen, Regression-Suite | Mitigated |
|
||||
| R-03 | Reviewer-Verfuegbarkeit fuer ASIL-D | 3 | 4 | 12 | Self-Review dokumentiert (nur Demo) | Akzeptiert (Demo) |
|
||||
| R-04 | Gitea-Server-Ausfall | 2 | 4 | 8 | Lokale Klone, regelmaessige Backups | Mitigated |
|
||||
| R-05 | Apple-Cert-Ablauf ohne Vorwarnung | 3 | 3 | 9 | Renewal-Reminder + 30-Tage-Vorwarnung | Mitigated |
|
||||
| R-06 | Windows-Build-VM unzuverlaessig (busybox-PATH-Konflikte)| 4 | 2 | 8 | MSYS2 dokumentiert, alt PATH vorne | Open |
|
||||
| R-07 | macOS act_runner host-mode Cache-Bug | 3 | 2 | 6 | continue-on-error, dokumentiert | Open |
|
||||
| R-08 | Doorstop-Tooling-Kompatibilitaet bei Update | 2 | 3 | 6 | Eigenes traceability.py, kein doorstop-Dep | Mitigated |
|
||||
| R-09 | Wissensverlust bei Single-Person-Setup | 4 | 4 | 16 | Project Manual + Dokumentation pflegen | Open |
|
||||
|
||||
## 4. Risiko-Reviews
|
||||
|
||||
| Frequenz | Teilnehmer | Outputs |
|
||||
|--------------|-------------------------|--------------------------------------|
|
||||
| Quartalsweise| Project Owner + TL | Aktualisiertes Register, Action-Items |
|
||||
| Bei Aenderung| Betroffene Rollen | Risiko-Score-Update |
|
||||
| Bei Release | Project Owner + QA | Restrisiken-Bewertung |
|
||||
|
||||
## 5. Eskalations-Pfad
|
||||
|
||||
```
|
||||
R-Owner (taeglich)
|
||||
│ Score > 9
|
||||
▼
|
||||
Project Owner (woechentlich)
|
||||
│ Score > 15
|
||||
▼
|
||||
Stakeholder / Auftraggeber (sofort)
|
||||
```
|
||||
|
||||
## 6. Lessons Learned
|
||||
|
||||
Geschlossene Risiken werden bei Projektabschluss in `docs/lessons-learned/`
|
||||
zusammengefasst, um in Folge-Projekten besser einschaetzen zu koennen.
|
||||
|
||||
## 7. Verwandte Dokumente
|
||||
|
||||
- `PM-Plan.docx` — Top-Level-Risiken (Auszug)
|
||||
- `HARA.docx` — Funktionale Sicherheits-Risiken (Hazards, getrennt von Projekt-Risiken)
|
||||
- `QA-Plan.docx` — Non-Conformity-Management
|
||||
|
||||
## 8. Aenderungshistorie
|
||||
|
||||
| Version | Datum | Aenderung | Autor |
|
||||
|---------|-------------|---------------------|-------------|
|
||||
| 1.0 | 2026-05-12 | Erstfreigabe | S. Lohmaier |
|
||||